Why BUA terminal was decommissioned, by NPAFRESH facts emerged on Monday on why the management of the Nigerian Ports Authority (NPA), decommissioned BUA Ports and Terminals Limited, operator of Terminal B, in Port Harcourt, Rivers State.

Speaking at the quarterly stakeholders meeting organised by NPA in Port Harcourt, its Managing Director, Ms Hadiza Bala Usman said the agency, as a responsible government organisation, took the step to save the lives and limbs of those working at the terminal.

She said the decision was taken for health and safety reasons after receiving a letter from BUA on security challenges surrounding the quays wall at its terminal.

She said the terminal operator wrongly served the NPA a contempt of court letter, arguing that the Agency has not violated any court order that restricted it from terminating the concession agreement it had with BUA by decommissioning the terminal.

The MD wondered why BUA will want to continue operating from a terminal that it termed unsafe in a letter it sent to NPA.

She said: “This morning, we have been served a contempt of court while arriving Port Harcout today. In November 2016, a notice of termination was issued to BUA Terminal for non-compliance with the port development plan. As part of the concession agreement, there are certain development that each terminal operator is supposed to do at their terminals. In line with the concession agreement, BUA was required to rehabilitate and reconstruct that particular terminal, but it did not do that for years.

“When NPA did an inspection, their concession agreement was terminated for failure to adhere to that development plan.

“However, BUA instituted a court injunction that prevented NPA from taking over the facility.  We got the injunction in January 2018. So between January 2018 to June 2019, BUA enjoyed using the terminal in totality with collapsed quay walls and berths. “We now received a letter from the same BUA, drawing our attention to the fact that the condition of the quay wall was deteriorating and not safe and it is at the point of collapse, and that they are very concerned.

“As a responsible regulator we looked at the state of that quay, and wondered how BUA could have used it for one and half years in that terrible state. With safety issues uppermost, we had to decommission the BUA terminal based on health and safety reasons.

“Now, the same BUA has gone to court to restrain NPA from implementing the decommissioning policy despite highlighting in their letter to us that the terminal is not safe. I am curious to what contempt of court this is all about. We are talking of an unsafe terminal.

“They are drawing attention of the public and alleging unfair treatment, but we are questioning what unfair treatment is in issues that have to do with safety.  Do we ignore safety and allow BUA to continue to use a terminal that is about to collapse?

“It is important to NPA that BUA notifies the stakeholders and the court that they wrote to NPA in that regards. They should stop attributing the decommissioning to termination issue because the rule in port operation business is safety first.

“We should be responsible as private entities by adhering to what is required of us and go through due process. In addition, we have noted the fact that the quay walls along the Port Harcourt Port are weak and they are at the point of collapse.”

Previous Article

lPMAN warns of impending fuel scarcity

Next Article

Dangote eyes $30b revenue

You may also like

Leave a Reply

Your email address will not be published. Required fields are marked *